hide You are viewing an archived web page, collected at the request of Princeton University Library using Archive-It. This page was captured on 20:37:02 Aug 09, 2017, and is part of the Princeton University Archives collection. The information on this web page may be out of date. See All versions of this archived page. Loading media information
Skip over navigation

Project Schedule

Construction of the Arts and Transit Project began in 2013 and was completed in fall 2017. Construction milestones for the project include:

Early Spring 2013   Demolition and site mobilization
Summer 2013   Construction of new commuter parking lot and temporary train platform; Alexander Street utility relocation
Fall 2013   New commuter parking lot and temporary train platform open; renovation of existing station buildings begins
Fall 2013-Early 2014   Construction of Alexander Street-University Place roundabout
Fall 2014   New train station, Wawa and transit plaza open; access road from Alexander Street to West Garage (Lot 7) opens
Fall 2017   Arts buildings open